Grand Gulf ups stake in Red Helium, set for Jesse#1A workover

Grand Gulf set to soar with a larger stake in the Red Helium Project in Utah. Pic via Getty Images.

share

Grand Gulf now has more skin in the game at the Red Helium project after increasing its working interest from 55% to 70% after meeting earn-in requirements for the first well.

It follows the company contributing the first US$1.5m for the cost of drilling the successful Jesse#1A well in Utah, which had intersected a 203 foot (61.85m) gas column with gas concentrations ranging from 0.44% to 0.65%.

This is above the 0.4% helium concentration found in the producing Doe Canyon project, while bottomhole pressures are in line with virgin pressure modelling at Doe Canyon.

Grand Gulf Energy (ASX:GGE) now has the right to boost its stake in the project to 85% by contributing the first US$1.5 million to each of two further Red Helium project wells.

Well testing to begin soon

The company has also sourced a workover rig, which is scheduled to mobilise to the Jesse#1A well site in mid-August.

It will pay 70% of the costs incurred above the initial US$1.5m expenditure associated with the well.

Work to be carried out by the rig includes running a production log, isolating the gas column and carrying out flow testing to determine reservoir deliverability and obtain a representative helium sample.

Grand Gulf had previously been unable to carry out stable flow testing at the well due to water ingress and reservoir pressures being sub-hydrostatic.

 

This article was developed in collaboration with Grand Gulf Energy, a Stockhead advertiser at the time of publishing.

This article does not constitute financial product advice. You should consider obtaining independent advice before making any financial decisions.

Categories: Mining